CONSTRUCTION PERMITTING OFFICER


Question 1:
a.       Make a checklist of all elements required when applying for a construction permit
SOLUTION:
1.      Project brief including a description of methods and techniques applied except for category 1
2.      Site plan including landscaping topography
3.      Copy Geotechnical report except for category 1
4.      Copy of environmental impact assessment report except for category 1
5.      Architectural drawings
6.      Structural design comprising plans and calculations except for category 1
7.      Mechanical, electrical, sanitation technology and fire safety plans as applicable except for category 1
8.      Bill of quantity and cost estimation except for category 1
b.      According to the Rwanda building code, define the increment building
SOLUTION:
Any dwelling house that for reasons of affordability is to be constructed in stages in such manner that in its intermediate stage the house can be occupied by its owner for the limited specified period of time necessary to complete it and that is intended, in its final approved form, to have a total plan area of not more than 80m2


c.       For an increment building only one occupation permit will be provided at the completion of the project. True or false. Explain your answer
SOLUTION:
True.
d.      What are the types of construction permit used in Rwanda?
SOLUTION:
Subject to the provisions of Article 83 of the Law No. 10/2012 of 02/05/2012 Governing Urban Planning and Building in Rwanda, a permit shall be required for:

1.      Development /New construction;
2.      Extension (vertical/ horizontal);
3.      Refurbishment of existing building with structural alteration;
4.      Rehabilitation and refurbishment without structural alteration;
5.      Occupancy;
6.      Change of use/occupancy; and
7.      Demolition (full or partial).
Question 2:
a.       Define a critical load for members in compression
b.      What is the difference between expansion joint and seismic joint of a building?
c.       According to the Rwanda building code, is the inspection of a foundation of a new building mandatory? Yes, or not?
d.      According to the same code for big construction projects, is it the responsibility of the contractor or that of supervisor to apply for the construction permit to the competent authority?

SOLUTION:
According to the Rwanda building code, the construction permit application must be done by the client.
e.       Make the difference between the results from the dynamic penetrometer and those from the direct shear.
Question 3:
Look at the beam in reinforced concrete (its self-weight is neglected) on the figure above. Provide diagrams of shear and bending moments in elastic domain, and propose a sketch of reinforced based on the diagrams (without any further design)