1.
Minimum thickness of slab is 125 mm.
2.
Water absorption should not be more than
15 %.
3.
Dimension tolerance for cubes + – 2 mm.
4.
Lapping is not allowed for the bars having
diameters more than 36 mm.
5.
Chair spacing maximum spacing is 1.00 m
(or) 1 No per 1m2.
6.
For dowels rod minimum of 12 mm diameter
should be used.
7.
Chairs minimum of 12 mm diameter bars to
be used.
8.
Longitudinal reinforcement not less than
0.8% and more than 6% of gross C/S.
9.
Minimum bars for square column is 4 No’s
and 6 No’s for circular column.
10. Main
bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and
the distributors not less than 8 mm and not more than 1/8 of slab thickness.
11. Minimum
thickness of slab is 125 mm.
12. Dimension
tolerance for cubes + 2 mm.
13. Free
fall of concrete is allowed maximum to 1.50m.
14. Lap
slices not be used for bar larger than 36 mm.
15. Water
absorption of bricks should not be more than 15 %.
16. PH
value of the water should not be less than 6.
17. Compressive
strength of Bricks is 3.5 N / mm
18. In
steel reinforcement binding wire required is 8 kg per MT.
19. In
soil filling as per IS code, 3 samples should be taken for core cutting test
for every 100m2.
20. Compressive
strength of Bricks is 3.5 N /mm2.
21. Maximum
Free fall of concrete allowed is 1.50 m.
22. In
soil filling as per IS code for every 100 sqm 3 sample for core cutting test
should be taken.
23. Electrical
conduits shall not run in column.
24. Earth
work excavation for basement above 3 m should be stepped form.
25. Any
back filling shall be compacted 95% of dry density at the optimum moisture
content and in layers not more than 200mm for filling above structure and 300
mm for no structure.
26. F
soling is specified the soling stones shall be laid at 45° to 60° inclination
(and not vertical) with interstices filled with sand.
27. A
set of cube tests shall be carried out for each 30 cum of concrete / each
levels of casting / each batch of cement.
28. Water
cement ratio for different grades of concrete shall not exceed 0.45 for M20 and
above and 0.50 For M10 / M15.
29. For
concrete grades M20 and above approved admixture shall be used as per mix
design requirements.
30. Cement
shall be stored in dry places on a raised platform about 200mm above floor level
and 300mm away from walls. Bags to be stacked not more than 10 bags high in
such a manner that it is adequately protected from moisture and contamination.
31. Samples
from fresh concrete shall be taken and at least a set of 6 cubes of 150mm shall
be prepared and cured. 3 Cubes each at 7 days and 28 days shall be tested for
compressive strength. The test results should be submitted to engineer for
approval. If results are unsatisfactory necessary action/rectification/remedial
measures has to be exercised.
32. Water
used for both mixing and curing shall be clean and free from injurious amounts
of oils, acids, alkalis, salts, sugar and organic materials or other substances
that may be deleterious to concrete or steel. The ph. shall be generally
between 6 and 8.
33.
Calculating Cement, Fine Aggregate & Coarse Aggregate for Mortar Mixes
For example, consider 1:4 mortar, 1 cum of cement mortar work is to be done
1:4 means 1
part of Cement by volume 4 parts of fine aggregate by volume
Total volume = 1 cum
Quantity of Cement = (1/ (1+4)) x
1 = 0.20 cum
1 cum of Cement = 1441 Kg
Cement quantity required = 1441 x 0.20 = 288.2 Kg
1 cum of Cement = 1441 Kg
Cement quantity required = 1441 x 0.20 = 288.2 Kg
Quantity of
Sand = (1/ (1+4)) x 4 = 0.80 cum
We have not done it correct; the above
quantity would yield hardly 0.63 cum of mortar because we have not
considered voids & cavities. So, we have to increase quantity by
50 – 60%.
So, the final
quantity for producing 1 cum 1:4 mortar is
Cement = 288.2
+ 60 % (for voids & cavities) = 288.2 x 1.6 = 461.12 Kg
Sand = 0.80 +
60 % (for voids & cavities) = 0.80 x 1.6 = 1.28 cum
Following
are few general points to remember for civil site engineers to make the
construction work easier while maintaining quality of construction.
·
Lapping is not
allowed for the bars having diameters more than 36 mm.
·
Chair spacing
maximum spacing is 1.00 m (or) 1 No per 1m2.
·
For dowels rod
minimum of 12 mm diameter should be used.
·
Chairs minimum of
12 mm diameter bars to be used.
·
Longitudinal
reinforcement not less than 0.8% and more than 6% of gross C/S.
·
Minimum bars for
square column is 4 No’s and 6 No’s for circular column.
·
Main bars in the
slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the
distributors not less than 8 mm and not more than 1/8 of slab thickness.
·
Minimum thickness
of slab is 125 mm.
·
Dimension
tolerance for cubes + 2 mm.
·
Free fall of
concrete is allowed maximum to 1.50m.
·
Lap slices not be
used for bar larger than 36 mm.
·
Water absorption
of bricks should not be more than 15 %.
·
PH value of the
water should not be less than 6.
·
Compressive
strength of Bricks is 3.5 N / mm2.
·
In steel
reinforcement binding wire required is 8 kg per MT.
·
In soil filling as
per IS code, 3 samples should be taken for core cutting test for every 100m2.
Density of Materials:
Material
|
Density
|
Bricks
|
1600 – 1920 kg/m3
|
Concrete block
|
1920 kg/ m3
|
Reinforced concrete
|
2310 – 2700 kg/ m3
|
Curing time of RCC Members for different types of cement:
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals & Admixture added cement: 14 days
De-Shuttering time of different RCC Members
RCC
Member
|
De-shuttering time
|
For columns, walls, vertical form works
|
16-24 hrs.
|
Soffit formwork to slabs
|
3 days (props to be refixed after removal)
|
Soffit to beams props
|
7 days (props to refixed after removal)
|
Beams spanning upto 4.5m
|
7 days
|
Beams spanning over 4.5m
|
14 days
|
Arches spanning up to 6m
|
14 days
|
Arches spanning over 6m
|
21 days
|
Cube samples required for different quantity of concrete:
Quantity
of Concrete
|
No. of cubes required
|
1 – 5 m3
|
1 No’s
|
6 0 15 m3
|
2 No’s
|
16 – 30 m3
|
3 No’s
|
31 – 50 m3
|
4 No’s
|
Above 50 m3
|
4 + 1 No’s of addition of each 50 m3
|
leases and load transfers that are worked out during
the design stage will not be achieved and this poses a serious liability on the
structural stability. It is important for us to remember that calculations
worked out on a piece of paper will mean nothing if we are not able to
co-relate them with practical conditions.
No comments:
Post a Comment