Wednesday, September 7, 2022

Supervision of Stone Masonry Construction

 


The following points should be kept in mind in supervising stone masonry work:

1.  Hard and durable stones, free from defects like flaws, cavities veins etc.  should be used.

2. Dressing of the stones should be as per the requirement.

3. Stones should be properly wetted before they are used so as to avoid sucking of water from mortar.

4.  Stones should be laid on their natural bed.

5. Facing and backing faces should be laid neatly and levelled and checked with wooden template.

6. The heart of masonry should be filled with stone chips and mortars.  To thick mortar joints should be avoided.

7. Verticality of the wall should be frequently checked with plumb-bob.

8. Mortars with correct proportion of sand and cement should be used.

9. Continuous vertical joints should be avoided.

10.  Through stones should be used within 1.5 m distances.

11. The height of masonry should be raised uniformly.

12.  Under the beams, trusses, sills etc large flat stones should be used.

13. Before continuing work, the masonry built on previous day should be well cleaned and freed from loose particles.

14.  Curing should be done properly for 2 to 3 weeks


Points to be Observed in Supervising Brick Masonry Constructions

The following points should be observed in the construction of brick masonry:

1. Use bricks of good quality with uniform colour, well burnt, with exact shape and size.

2. Before using the bricks in masonry, they should be soaked in water for 2 hours so that bricks do not absorb water from the mortar.

3. Bricks should be laid with the frog pointing upward.

4.  Construction of brick wall should start from the end or corner.

5. Brick courses should be perfectly horizontal.

6. Verticality of the wall should be ensured by frequently checking with plumb-bob.

7. Mortar used should be as per specification.

8. Whenever work is stopped brick masonry should be left with toothed end.

9. Use of brick bats should be avoided.

10.  Walls should be raised uniformly.  In no case difference between adjoining walls be more than 1   m. In a day no wall should be raised by more than 1.5m.

11. To get proper key for plastering or pointing, the face joints should be raised to a depth of 12 to 20 mm, when the mortar is green. If plastering or pointing is not to be provided, face joints should be stuck flush and finished neatly.

12.  Holdfasts for doors and windows should be embedded in brick masonry with cement mortar or concrete, at the time of constructing the wall itself.

13. Brick masonry should be regularly cured for 2 weeks.

14.  For carrying out brick work at higher levels, only single scaffolding should be used.

No comments:

Post a Comment